what is the quantity of cement( in bags),sand and aggregates required for 1 cmt of M 25 concrete
Answer Posted / harika nukala
M25= 1:1:2
VOLUME = 1+1+2=4
TOTAL VOL OF DRY MIX =1.54
CEMENT = 1/4(1.54*1440)=554.4 Kgs = 554.4/50 = 11 BAGS
SAND= 1/4(1.54)= 0.38 CUM
AGGREGATE = 2/4(1.54)= 0.77 CUM
Is This Answer Correct ? | 6 Yes | 2 No |
Post New Answer View All Answers
I was once rejected for US visa in early August. But now I'm going again for interview next week. What are the chances that I will faced the same VO????
Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....
Slump Values for works?
What are the causes of building collapse?
Why the finite element method is lower bound solution?
What is Heavy Concrete & Normal Concrete
Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.
can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???
What are the methods in tiles flooring ? What are the methods in brick work? What are the methods in plastering ? What are the methods in wall tiling?
16 questions out of 55 were from the book GUPTA N GUPTA OBJECTIVE of civil engineering. Total ques were 4 ques from hydraullics, 7 from BMC, 4 FROM SOM, 4 from soil mechanics, 6 from transportation, 5 from engineering drawing.
How do you calculate the power of a centrifugal pump?
Hi how r u ? hope you are fine there . Please can u tell me tha Design life of Buildings as Per ACI CODE 318-99. It will be a pleasure for me .Thanks in advance
What quantity of 1.0 m3 bricks required?
Hi I had missed my mark list (first year-apr2003)how i search in my old mark details in internet and which web site? pl inform me in full details..
How to do rate analysis for concrete work including shuttering work?