if 2mmarow is release and 2-day You found a critical bug wat
you will do ? plz give answers
Answer Posted / daniel
MY answer is from the TPM or PM point of view
- Assessment the impact of this critical bug – which area/feature get affected.
- Find out any workaround in case the bug cannot be fixed
- Set a 24 hours urgent plan for fixing and testing and also getting the time for resolution/testing
- Provide recommendation for go or no go decision for final decision maker
- If go with this critical bug, release note need to cover the issue and how to recover
- If no go, the timeline for patch release.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
In testing environment have you ever found any areas for improvement while you at work. (Please give some real life example).
Explain what is exhaustive testing?
What does you mean by positive and negative testing & what is the difference between them. Can anyone explain with an example?
In what situation would you want to parameterize a text verification check?
What is decision table testing?
Give the real-time example for back-to-back testing?
What are the queries mostly asked in testing ? give me some examples.
If date field is a text field write test cases to validate it?
If there is non reproducible bug which developer is not ready to agree, how you will convince him.
How could you present test strategy for the product testing?
what are questions asked in TCS for database tester (sqlserver)?ay idea
What is difference between cmmi and cmm levels?
Differentiate verification and validation?
How can I use bugzilla in my company to track a bug and to allow the client to see the bug report online throughbugzilla. Please explain in detail. I am really need this.
What do you like about computers?