what is the ratio of M10,M20,M30,M40,M50,M60 grade concrete
Answer Posted / d.s.priyadarshi
M5-1:5:10
M7.5-1:4;6
M10-1:3:6
M15-1:2:4
M20-1:1.5:3
M25-1:1:2
and above as pr IS code mis design
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
In a concrete grade C35A, C & A stands for what and equalent cube strength?
on what basis the partial factor of safety are decided? form the load combinations
Can we apply curing compound on ceiling (slab Bottom)
how much concrete solid/hollow block are manufacture per 50 kg cement bag in differnent sizes like 400x200x200mm, 400x200x150mm, 400x200x100mm. And need proper ratio as per sale quantity. pls send my mail mathi7599@gmail.com searching last two years not yet get pls find and enclosed pls. need practical analysis.
how to calculate quantity of bricks in circular manhole with examples.
What is the difference between Rock And Murrum. How to claim that excavated material is not a murrum but rock.
Define What is the difference between routing maintenance and major maintenance in school facilities?
Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
In cement making,what is meaning of blend,fineness,density.
what does the track parameter mean in staad.pro?
What is thumb rule for deep trench excavation
how many minimum admixtures are used in water froofing structures
foundation details for 25 ton weight Furnace on 2 supports and 2 tilters
what are the Task work of different labour.?