Answer Posted / deoghar
Suppose that total length is : 50.00 mtr
Dia of Bar : 32mm ( Lap length is 1600mm )
Then total length is
= 50.00-6.00mtr = 46.00mtr ( 6.00 is 1st Bar)
( 6.00-1.600 = 4.400mtr)
Now 46.00 / 4.4 = 10.450 + 1 =11.45no
You Can say 11 no of lap found
Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
how much tempareture are required to make liquid state of pid leed
What is costing in 100squre feet bricks
psc girder detail
how many shuttering material required for 1000 sq.m built up area.
How much does it cost for a R.C.C cover slab of size (450mmX 600mmx 100mm) double rf net given in feets using hand mix concrete?
In case if concrete box girder bridges how is the number of cells determined?
Describe the various methods of concrete curing?
What was asked in isro civil interview
A Cat excavator loader of 3Lm*3 heaped capacity bucket is to be used to load blasted rock directly into a crusher of capacity (consumption) of 100L
How high should the water tank be to provide a 60 psi at base of this water tower?
what is directivity effect?
Why should pumping be not used in case of concreting work?
Power grids in two adjacent states(A&B) are interconnected. Can power grid in state A can be represented by Thevenin Equivalent Circuit. If not explain Why?
what is mean by reestimation?
How to estimate the shuttering material requirement for a slab and beam and shear wall..? Please send thumbrule to estimate material required ( Plywood, Ms plates, runners, acrospans, jacks)