what is the curing time for plastring (all)?

Answer Posted / shadavali123@gmail.com

All plaster curing time 7 days

Is This Answer Correct ?    14 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

In a beam,stirrups are placed closely at ends than at centre due to shear.similarly where would ties be closer to each other-at center or at ends in a column and slab.

2854


Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day

1582


what is smart building materials?

1588


What sizes of stones chips are used for foundation, column and floor casting. Please answer in detail.

1679


how many running meters in one kilogram of 4mm pvc coated chainlink fencing

637






Suppose you planning to paint newly fabricated workshop building made of structural steel of 10 tons total mass. How many litters paint primer for 1 coat and 2 coat of top coat?

3018


Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?

1644


What is the basic difference between OPC

1421


How does siphoning work?

822


how to calculate labour strength for work for RCC,brickwork,blockwork,in &out plaster,flooring,dado,door frame & shutter,painting etc for constructing highrise building?

3316


115mm thickness brick work how to required mortar

1628


SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?

2243


foundation details for 25 ton weight Furnace on 2 supports and 2 tilters

1105


I Want To Know Quantity of Cement Conc. & Sand in Column of 9"x9"x10'

2041


how to disign cuplock shuttering and it's matireal requirement snd any related web site

2511