Before erect the instrument what should you do?
Answer Posted / fazil
one should have work permit..operator will control the signal manually.. close primary valve and manifold also
drain existing liquid or gas by drain plug.
remove termination and glanding also tape it to avoid short.then you can remove instruments
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
How vortex sensor used for steam flow measurment can be checked on line i.e without taking out from process line.
Draw bode plot of any transfer function. Why is plotting bode necessary?
Define the difference between a stable versus an unstable controlled system and some of the tools you might use to be able to detect when this is happening and assumptions used for control system application design that could contribute to instability
How to convert mmWc(mili meter water colam) to tph(ton per hour)?
kindly sent some demo question and answer
Actual using of tube bender to bend 2 opposite 90 deg at correct measurement center to center of tubing.
what is metal of piston ring
why I need valve guard and whats different between guard and positioner ??
I want to buy a seal kit of a pneumatic power cylinder.But I don't know it's specification.So please help me to know its specification.
how to calibrate corollaries (Mass flow meter)?
how pressurize drum calibrated ?
how many types of spped sensors n vibration sensors?their basic principle n connection?
Explain the difference between plc and cnc?
I m appointed as an automation trainee engineer in small firm in that I am only the one , my company give me a project on s7-200 as i m beginner I don't know how to program so please send me the helpful site so that I complete my project before deadline....please help me out in this critical situation.
we have level transmitter for h2s04 storage tank capacity 10k ,always there are failure of transmitter due to failure of magnetic floats ,please come up with solutions at the earliest.