Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

What is a BBS?Find out the cutting length for a foundation size 600 x 600, cover 50 mm?

Answer Posted / piyush singh

BBS Stands for Bar Bending Schedule.

For a 600mm *  600mm Foundation and 50 mm cover 

Cutting length will be 

= 600-left cover - right cover
=600-50-50
=500mm

Is This Answer Correct ?    4 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how to calculate MR 9(derivation)

3035


how to calculate quantity of bricks in circular manhole with examples.

5780


how we calculate the vol.of wet concrete..?

1936


What is the density of most of construction materials?

1283


What is the effect of a building collapse?

1321


What is the procedure of concealed plumbing in toilets?

2430


I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

2140


What is zoning permit?

1264


how to calibrate the RM 800

2463


How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.

1582


In a beam,stirrups are placed closely at ends than at centre due to shear.similarly where would ties be closer to each other-at center or at ends in a column and slab.

3383


How can we make a hole in a solid rectangle using solidsworks?

1342


What are the ingredients of pre-stressed concrete?

1302


What is the material consumption- cement,sand,tiles etc for Toilet dado?

7796


what is the criteria for the finalisation of pavement thickness in road project?

2187