Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

what"s the formula find the cement consumption for brick work
23 thick wall 1 m3?

Answer Posted / gowtham1993

(1/(0.2*.1*.1))=500

=500*(.19*.09*.09)=0.76 cum of brick volume

=1-.76 = 0.24 mortor volume
=0.24
so
for 1:4 cement mortor it require 1% cement and 4% sand

0.06 cu.m of sand is required

Is This Answer Correct ?    6 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to find out slope footing concrete

2885


if i have to draw bending moment diagram of 4 way continous span then how to create it and how to find reaction?

1945


Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?

1770


what is the water-cement ratio of mix design while 30mpa in 7 days?

3008


50 acre of land to be reclaimed for an average height of 2.5 mt. Dredging area is 500mx200m size. what is the dredging depth required to reclaim the area?

1909


from one meter cube of stone masonry structure how much cubic meter of cement mortar we use as our estimation 25-30% is that correct for estimation of quantity of sand and cement(2:1) proportion of mortar

4594


How reactor of SBR installed , is it be over ground, fully under ground or semi sunk ?

2272


Explain creep?

1063


what mean By core Billing

2266


what is meant by sustainable developement as far construction field is considered. Give suitable examples to explain the same

2164


what are the Task work of different labour.?

2583


what is modular brick and it size

1665


How to arrive the co- efficient of all civil activities? For ex:- painting-enamel in wooden doors. co efficient is 1.8. How this is calculated

2120


strength vs shape factor

2495


how to calculate freeboard in under ground water tank and technical details

3338