what"s the formula find the cement consumption for brick
work 12 thick wall 1 m2?

Answer Posted / dj_mgood

It's Depend on ratio of morter.

formula is very simple.
Quantity of wet material x 1.27 = Dry morter,
Example, let suppose wet material is 100cft then
100 x 1.27 = 127cft
requied material / some of ratio
if morter is 1:4 then
1/5 * 127 = 25.4 cft
25.4/1.25 = 20.32 say 21 bags

if thickness of plaster is 1/2" then it cover 508sft Area.

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

plz.show development and anchorage length in simple diagram.

2640


can any one give me sample question paper of BHEL at mdansari86@gmail.com as i m appearing for the same exam.

2236


how can we calculate steel value, depending on load

2444


pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer

3239


water leak detection system question & answer

2526


can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now

2240


PLS.......... ANY ONE CAN FORWARD ME PREVIOUS QUESTION PAPER hpcl civil engg

2425


how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?

2226


can u plz send me ntpc placement papers(civil engineering) at mohit_verma21@yahoo.com

2594


manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.

1842


400 ku d/c clearess ketan hota hai?

2124


In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

2237


pls mail some more tecnical qustions at msaranya2610@gmail.com

2183


can i get civil engineering test papers.......?????

2550


How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 100 microns?

1618