how can change 12mmdia@150c/c bar spacing to 16mmdia
Answer Posted / abiraj07
D1^2/S1 =D2^/S2
12^2/150 =16^2/S2
0.96 =256/S2
S2 =256/0.96
S2 =266.66MM
Is This Answer Correct ? | 8 Yes | 0 No |
Post New Answer View All Answers
What is the coeffiencent Friction Angle between Steel and Ashphalt?
How do we test on design and style in a software?
Determine the production capacity of a treatment plant for a city of 1,250,000 population. Assume the specific consumption per capita of 15ol/c/d, non-domestic water use of 30,000,000 m³/year, and UFW of 12%.
Calculate the maximum allowable speed on a horizontal curve of radius 350m if the maximum allowable values of the lateral coefficient of friction are 0.14 and the rate of superelevation is 0.08.
detailed calculation of the amount of cement used?
The concrete slump recommended for beams and slabs; is?
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
how to calculate mivan shuttering matrial
A sieve analysis results in 100% retained in no. 50 Sieve, the fm is?
Hi I had missed my mark list (first year-apr2003)how i search in my old mark details in internet and which web site? pl inform me in full details..
For the calculation of bearing pressure below the footing, to know whether it is below the safe bearing pressure of the soil, the unit of RCC below ground level to be taken is 25 KN/m3 or (25-15)KN/m3, where 25 is the unit weight of RCC and 15 is the unit weight of soil and whether the weight of backfilling to be taken?
how much cement sand n bricks required in im3?and how much in plaster?
brickwork labour rate per cum ?
what is the steel difference between np-2 and np-3 pipes and weight also
how to find quantity of concrete in PCC M15