HOW MANY CEMENT BAGS ARE REQUIRED IN 1 CUBIC METER
Answer Posted / mj
its depend on grade.
grade bages
M 20 6.8
M 25 7.5
| Is This Answer Correct ? | 5 Yes | 1 No |
Post New Answer View All Answers
For a washout valve why are two gate valves required in normal practice?
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
What is quantity of cement and sand required for 2000sqft of tiling?
Cement consumption of one cubic meter of aerocon blocks masonry?
Explain the different types of building contracts?
for G+2 residential building how much quantity of required in foundations,sub & superstructures per sq ft area
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
How to produce the Concrete Grade 30mpa at 12hour? How to prevent for plastic shrinkage crack? How can we produce fire resistant concrete?
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?
What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet
What is the average density of soil?
I need to do a Compressive Strength Test for a specimen made of Rubber. Before doing the Test on the Machine, I need to have an idea of the Minimum and Maximum Compressive Strength or Yield Strength of the specimen. How can I calculate that?
what are the code used for residental building?
how many mason and labaur work for a 1 brass bricks plz let me know the calculate & how to made calculation for this and whats the formulas for this?
Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required