1 cft of brickwork 1:6 mortar ratio need 12 numbers of bricks so find the quantity of sand and number of cement bags
Answer Posted / sunil jain civil engineer katn
CEMENT AND SAND 1:6 BRICKS WORK IN USE
CEMENT 58 KG PER/CUM ( 1CUM = 35.28 CFT)
SAND 0.243 CUM PER/CUM (1 CUM =35.28 CFT)
CEMNT 58/58= ANS.1.64 KG PER/CFT QFT BRICK WORK
SAND 0.243x35.28=8.5 PER/CUM
8.5/35.28= ANS..24 CFT PER/QFT BRICK WORK
| Is This Answer Correct ? | 3 Yes | 4 No |
Post New Answer View All Answers
What is meant by autocad?
what is the formula for Mass of cement grout (Dg)=???
How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?
Define current ucs?
What is made from large rocks, which protects the base of cliffs?
Who name us Engineer & Why?
How to measure the requirement of cement n sand for 12mm and 20mm plastering thanks in advance
20mm thick sand face plaster on walls consisting of 12 mm the backing coat of c.m.(1:3)and 8mm thick finished coat of c.m.(1:1)including scaffolding, watering, finishing etc complete please calculator with methyl et et r u
how many tonnes equals to one cubic feet?
Define What is the meaning of a blue land surveyors flag?
A 16 pile group, consisting of diameter concrete piles, were cast in situ in a clayey soil whose unconfined compressive strength is 1100 psf. Each pile is 60 ft long and the pile spacing is 2.5 times the pile diameter.The water table is at the ground surface and saturated unit weight of the clay is 118 lb/cu.ft. using a factor of safety 3 and a reduction factor =0.45, compute the allowable capacity of the piles acting as individuals
How to activate isometric axes in cad?
How to do rate analysis for concrete work including shuttering work?
why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?
how much repeitation for conventional and maivan formwork?