how to calculate concrete qty for footing using M25 grade
1:1:2 for 731 cft.
Answer Posted / vijayababu`
M25 – 1:1:2
Total parts – 4
Cement Required for 1 cum =1/4X1.57X1440
= 0.393X1440 = 567kg/cum
= 11.34 bags/cum
Is This Answer Correct ? | 17 Yes | 3 No |
Post New Answer View All Answers
B.M DIAGRAMS & S.F DIAGRAMS OF CONTINOUS BEAMS
how much percent are used 20mm,10mm?
what else we can add rather than admixture in concrete to reduce the cement quantity?
What are the responsibilities of a site manager?
what are the values of compressieve strenght?
. Write a C program to perform following functions:- a. Declare one integer variable of all the storage classes. b. Print all the variables without assigning any values in tabular format. a. The tabular format must contain the variable name, type, storage class and printed value on the screen in RED color.
What is the material consumption- cement,sand,tiles etc for Toilet dado?
What are the advantages of cad?
material used for mendrel use to bend epoxy coated rebar
what is education Cess.
Can inverted beams used in pipes during construction? If yes, explain how it can be implemented?
Is there the dry coefficient of cement is constant?
whou haat goals do you have in your career
Minimum and maximum size of the building components
What does civil status mean?