Answer Posted / sfz ans
Its (D*D)/162 = Unit wt of Tor steel/meter length.
This formula is controversial for huge project ie: estimated Steel usage upto 20k tons.
There we have to go to basics ie: volume x unit wt.
eg: 10mm Tor bar = [3.14 x (D*D)/4] x 1 x 7850 = 0.616225 kg/m
where D= dia in meter
OR
eg: 10mm Tor bar = (D*D)/162 = 0.6178 kg/m
where D= dia in mm
from above examples you can see there is slight diff between two wts.
thus for the project of large quantum, basic formulae should be followed.
| Is This Answer Correct ? | 10 Yes | 0 No |
Post New Answer View All Answers
What is missing report and how to prepare
What is Rankine Cycle?
Slump Values for works?
How much quantity of cement and sand required for the inlining of 610mm dia MS pipe 8.7mm thk.Inlining thickness is 10mm and CM ratio is 1:1.5.
2. In a container filled with each of the following materials, at a porosity of 40%, determine the upward gradient required to cause the quick condition (a) Lead shot with a G = 13.75; (b) Fibre beads with G = 2.15; (c) Sand with a G = 2.32
if the nitrates more than 45mg/l in water lead to disease then what is it called
what is c4x light weight cement blocks
What are the different types of runners?
What in your opinion makes you the most suitably qualified candidate for this post of civil engineering technician?
how much of the strength comes from post-production curing
What is the difference between 53 grade and 43 grade cement
What is Joule Brayton Cycle?
why we are useing plastic under the lean concrete?and whts the advantage?
Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft
What is critical path method (c.p.m)?