Its (D*D)/162 = Unit wt of Tor steel/meter length.
This formula is controversial for huge project ie: estimated Steel usage upto 20k tons.
There we have to go to basics ie: volume x unit wt.
eg: 10mm Tor bar = [3.14 x (D*D)/4] x 1 x 7850 = 0.616225 kg/m
where D= dia in meter
OR
eg: 10mm Tor bar = (D*D)/162 = 0.6178 kg/m
where D= dia in mm
from above examples you can see there is slight diff between two wts.
thus for the project of large quantum, basic formulae should be followed.
| Is This Answer Correct ? | 10 Yes | 0 No |
Post New Answer View All Answers
What is meant by Crystal Concrete?
What are the points to be considered for calculating cement reconciliation. a)Do we need to deduct the wt of cement bags b)Do we need to adjust the qty due to wt loss during transportation, loading unloading etc or else each bag can be considered as 50 kg bag c)What is the proportion of mix cover block making.
Determine the production capacity of a treatment plant for a city of 1,250,000 population. Assume the specific consumption per capita of 15ol/c/d, non-domestic water use of 30,000,000 m³/year, and UFW of 12%.
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
What is the frequency of sampling for the materials of cement,Fine aggregate, Coarse aggregate .and refer which code
what is raft foundation
If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.
How to marking the building
Define graphics window?
what is the water cement ratio for plastering
on what basis the partial factor of safety are decided? form the load combinations
do we consider shrinkage factor for calculating cement consumption for CM mixes for different works?
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
i have four storeyed rcc building.basement of the building is around 34 years old.it does not have pillar support.it is having lintel steel support at every 7 feet of construction. how long this building will lost long . can any body help me in this regard
What is the primary difference between adsorption and absorption?