Answer Posted / krishnakanth jami
(i) Common building bricks—35 kg/sq. cm,
(ii) Second class bricks—70 kg/sq. cm,
(iii) First class bricks— 105 kg/sq. cm.
(iv) Crushing strength of bricks not less than 140 kg/sq. cm are graded as AA class.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
how many men days of loburs and masons are requirete for 1 cum,pcc (1:2:4),Pcc(1:3:6) and Pcc(1:4:8) thanking you
Describe the sections included in a typical bill of quantities
Hi my name is Binyam and I'm a 7th grader at Mayfield Woods Middle school. I decided to research civil engineering as my career and i need to know a few thing about your profession. What is your daily routine? What are some advantages and things you like about your job? What are some disadvantages What is the hardest thing you have done? What education have you gone through to become a civil engineer? How long is your work day? What is your work environment like? What is your salary? What made you want to become an engineer? What tools do you you use? Thank you for answering my questions
what discoveries did you have in relation to your course?
primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above
How to increase a bearing capacity of soil?
material used for mendrel use to bend epoxy coated rebar
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
What is the significance of cost estimate knowledge for an architect?
Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?
I am called for interview from north east power plant .so, I need some interview question which may help me.
What is the sugested procedure of water purification for public supply?
What is the use of offset command?
How many pyramid in egypt?
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?