How to calculate lap,bond and hook length for preparing bar
Bending schedule ?
Answer Posted / syed mohd. fareed
Hook - 9d (d- dia of bar)
Bent up - 0.42D (D- centre to centre vertical distance between bent portion and bar )
Lap - 50d (d-dia of bar)
| Is This Answer Correct ? | 50 Yes | 12 No |
Post New Answer View All Answers
load combinations how many types for staad design purpose?
Iwant to calculate the production of 1 labour for concrete casting which includes shuttering,scaffolding,steel fixing,concreting, deshuttering and curing in 8hours.But i am not able to determine it approximately would you pls.??
Concrete cover for slab, column, beam and footing?
how to calculate detail quantity of bricks and mortar for 500 cu.ft masonry work. consider wall thickness 9 inches
Explain what is progress payment?
what is meant by csr in foundation? what is sbc?what is meant by contour line?
How many days should curing of plastering, brick work and concrete
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
What is reinforced concrete?
find the discharge of water through a horizental venturimeter having 400mm dia at the inlet main and 150mm dia at thorat.if the diffrential gauge between inlet and thorat shows a pressure head of 25cm mercury. assume coefficient discharge 0.98 and specfic gravity of mercury as 13.6.
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
How can you distinguish between sorption, absorption and adsorption?
can any one give me sample question paper of BHEL at mdansari86@gmail.com as i m appearing for the same exam.
What are the causes of building collapse?
cause of cylinder test failure