Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How much overlaping required for welding the
reinforcement bars in Columns & beams

Answer Posted / kumaran

50 times the dia of the bar
that is (for 12mm *50)=600mm

Is This Answer Correct ?    1 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Draw a neat sketch showing the 'throat' of a welding in a plate girder ?

2503


how to calculate load bearing column

3641


what is the code provision for acceptance of fineness modulus range for fine aggregates in design mix

5276


How to calculate the crank rod in slab

2497


in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?

2372


Who name us Engineer & Why?

2579


What are the advantages of building a dam on the river nile?

1173


how much used soil in 1 brick of standard size?

2143


pls tell estimate for 1 kilometre length random rubble masonry 0.90 metre height 0.600 metre width

1632


Kindly post me previous year interview questions with answer for post of Manager (civil engg.) for NTPC, IOC , GAIL etc. I have interview on july 2013.I will be very grateful to you. Please guide me.

2312


how i convert mm into standard wire guage (SWG)no.

3129


how to reduce size of column 450 x 750 to 230 x.... if it is cut in area of bathroom? means it appears in bathroon any shifting or any other option....building is g + 10 and the bathroom is at first floor...

2425


how to determine H- zone in a column? where it will occur?

2249


I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

2141


What are new methods /technologies of pothole patching?

2462