Answer Posted / rajesh.d.v.s.p.
normal design per square meter of slab we take 15kg of steel
hear thay given 100 sq.ft
1sq.ft = 0.0928sqm
100sq.ft=.0928*100=9.2 sq.m
total steel requried = 9.2*15=138 kgs
| Is This Answer Correct ? | 8 Yes | 8 No |
Post New Answer View All Answers
How and where are aqueducts built?
what is the minimum cement content for M20 & M25 as per is code -456(2000).
Please let me know about answer for my Question as "What is the maximum wastage allowable of HYSD Steel in any Bridge project as per Code and Code reference also ?
how to calculate labour strength for work for RCC,brickwork,blockwork,in &out plaster,flooring,dado,door frame & shutter,painting etc for constructing highrise building?
How to avoid fly ash seed ball formations in the concrete mixer while mixing of raw materials for fly ash block manufacturing?
How is the leaning tower of pisa supported?
qty. of cement & sand required (100sq.mtr) for fixing of floor and wall tiles also fixing of marble stone on the floor
Define What is passive earth pressure ?
What is specific gravity???
what is civil enginnering & what you need of this course?
how to calculate number of bitumen for road asphalt
what is civil all interview questions
Exterior Joints,define
how to clculate the %of concrete strenght achive after curing?load
how to determine the correctness of proportion used in cement mortor and various IS codes to determine the same?