Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

if cement is 70 kg. sand is 140 kg and coarse aggregate is
280 kg. so what is volume of cement, sand and coarse
aggregate? please explane it.

Answer Posted / engr saleem mughal

cement=1.75cft sand=3.07 cft c agg=6.74 cft

Is This Answer Correct ?    7 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how to calculate cost of raw materials of a building for 1000 sqft & also consolidated cost of labour in a 1000 sqft building

2858


What is meant by engineering drawing?

1058


Which are the Steel tests ?

1237


3. What are the disadvantages of your present job, things you do not like about it?

2814


What are advancements in civil engineering?

1066


The mixture of different ingredients of cement is burnt at?

1639


how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar

2386


Iwant to calculate the production of 1 labour for concrete casting which includes shuttering,scaffolding,steel fixing,concreting, deshuttering and curing in 8hours.But i am not able to determine it approximately would you pls.??

2716


std penetration resistance in very stiff clays lies bet 2 & 4 4 & 8 8 & 15 15 & 30

2027


how to calculate total cost for slab 35'×8'

1929


What is the effect of a building collapse?

1229


how the calculation occurs if i want to mix 1cum of M50 concrete. please calculate every ingredients with detail calculation.

2178


How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.

2316


I just got a first job in Maharashtra and m a fresher. My task is estimate the cost of excavation of earth with J.C.B. can anyone tell me how to do this??

1841


whats is difference between anchorage length and development length

1873