Answer Posted / vikas gejwal

m10 1:3:6
M15 1:2:4
M20 1:1.5:3
M25 1:1:2
M30 depanding on mix design acoording to IS CODE

Is This Answer Correct ?    79 Yes 14 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

why do we not deduct volume of steel to find actual volume of concrete in practical???

1329


what is difference between GTS bench mark and temporary bench mark

3965


How to arrive d*d/162 , for finding the kg per meter , wt of steel

1406


how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.

3335


what is the code provision for acceptance of fineness modulus range for fine aggregates in design mix

4523






how many sqft or cft of work done by a mason per day in all works such as brick,block,concrete,shuttering carpenter,reinforcement fabricator,painter,door window carpenter.....everything thank you

1512


What is meaning of Canceled/Flat Beam. What is difference between them? Both type of beam can bear same load if size (width)of the flat beam is increases and depth is same as slab thickness? Kindly suggest to me.

1858


Which IS Code/American Code applied for coupler test of steel

2186


mix design procedure for 1:6 cement mortar

1745


how to find hardness of water?why it should be determined?

1587


If we buy crush sand for 3200/ Brass and cement for Rs350 /Bag and flyash 1200 / tonne....and my production is 230 Bricks per bag than how much cost is required for 1 flyash brick?

1720


Doul Bar reinforcement and details of drawing.

1929


what is the difference between np2 and np3 concrete mix

1564


material used for mendrel use to bend epoxy coated rebar

1853


How to get MEP technical,instaaltion & testing data for interview?

1612