How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer Posted / vipin kumar
Bricks=1/volume of 1 brick
1/.23*.115*.075=504 Nos of Bricks.
But Pricitaly=475 to 485 Nos of bricks(kyoki fat layer not proper 10 0r 12mm).
Sand&Cement =100 cum B/work in 30 cum sand,
Than
cement ratio=1:5
.3/1+5=.05cum dry mortar
(1beg cement volume=(1/28.8)=.0347
Than Cement=.05/.0347=1.44 Bags
Sand =.05*5=.25cum.
| Is This Answer Correct ? | 28 Yes | 12 No |
Post New Answer View All Answers
for G+2 residential building how much quantity of required in foundations,sub & superstructures per sq ft area
Can you pl explain the procedure steps of singly and doubly reinforced beams in limit state method
How to find out slope footing concrete
contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?
what is the weight of 6000 psi concrete in lb/cft?
Types of column foundation and how to calculate its steel quantity.
What is an object snap mode?
Specific gravity of cement?
a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.
how to find out hard strata in bored pile when the DMC method adopted.
How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.
What is the nature of duties & responsibilites senior civil engineer ?what is self confident & satisfaction should be a senior civil engineer?
What are advancements in civil engineering?
What type of tensile strength is handling by crank in beam? Thanks.
what is the sequence of the activities in the typical under ground water tank including civil & MEP works.