What is difference between PLC and SCADA
Answer Posted / guna
PLC - Programmable logic controller. Its a hardware, which is directly in contact with field instruments. it works according to the logic written in plc.(EX: like a computer hardware)
SCADA - Supervisory control and data acquisition. Its a software, which shows the out put feed back in visual manner, that plc cant do. (EX: like a computer screen)
| Is This Answer Correct ? | 18 Yes | 4 No |
Post New Answer View All Answers
What is Harmonics how it is produced and what is the method to control the same
How can get elongation of 2 k.G aluminium, if elongated aluminium dia is 2.5 mm?
how can i find ct ratio of meter by seeing name plate of meter and how it should be used in MF calculation if it shows only-/1???
can i connect the two phases of scott connected transformer,if not why?
Name of the relay of low lub oil presuure in DG sets
formula for calculation of switchgears(i.e. contactor, fuse, cb, relay etc.), if load current is given?
why it is so called as xlpe(cross linked poly ethyline) cable?
1))why we run three phase or three different circuit from a single conduit 2)) why not two circuit of different phase run in same conduit?? and why we run same three cicuit of same phae run in single conduit??
determine two methods to find loose connection in operational electrical system?
What is the formulae of Megger value for a A.C.Motor
what's the difference between abs/inc encoders. apart from the position remembrance what are all the other differences. and what's mean by grey code.
In MEP Services what are parts of STP and what are there function?
use of PIR in ehv breaker
how to check avr of dg set of 125kva
wat is the first thing dat is needed, 2 lay a cable in some area??