Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how to calculate cutting length of stirrups bar in beam

Answer Posted / manish bagga

suppose size is (200*300),Cover is 25mm ,than

200-50=150
300-50=250
than, (150+250)*2+Displacement lenth(10D)
Cutting Length=880

where, dia of stirrups bar =8mm

Is This Answer Correct ?    25 Yes 9 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Mention different types of roof systems?

1195


Differentiate first angle & third angle projection?

1139


Bernaullis theorem deals with the law of conservation of mass momentum energy none

2031


Explain what are the skills required to become an architect?

1177


What is meant by dimensioning?

1140


what is labour consume factor in residential projects

2382


What is the Tor steel Consumption for residential building G+24 footing (thum rule) ?

1860


if the nitrates more than 45mg/l in water lead to disease then what is it called

2928


how to take the quantity of block work and plastering  1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate

2472


sir iam dng my engg final yr (civil) iam intrested to write group_1 .if we write this exam what kind of jobs we get and what should be the minimum score for us to get qualified and iam having reservation too.

2899


in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh

2277


Dear Sir What is the Contraction joint for base Slab

2135


what isload waring calculation

2393


What is critical path method (c.p.m)?

1161


how much of the strength comes from post-production curing

2775