Plastering with cm 1:5 mix( one cement and five sand )
to 12 mm thick. How much Bag of Cement (50 Kg) and Sand (Cum)
Answer Posted / p. jairaj
Plastering in cm 1:5
1 part - cement
5 part - sand
total - 1+5 = 6 part.
Thickness of plastering - 12mm
Volume of mortar required for 1sqm
vol of mortar = 1.0 x 1.0 x 0.012 = 0.012cum.
volume of dry mortar of 1cum of wet mortar = 1.57cum
vol of dry mortar = 1.57x0.012cum = 0.01884cum.
vol of cement = 0.01884 ( 1/6) = 0.00314cum
Qty of cement in kg = 0.00314cum x 1440kg/cum = 4.5216kg
qty of cement in bags = 4.5215/50 = 0.0904 bags
qty of sand = 0.01884cum ( 5/6)= 0.0157cum.
| Is This Answer Correct ? | 11 Yes | 0 No |
Post New Answer View All Answers
pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer
what is the procedure involved in preparing mix design of m15 grade as per IS-10262-1982
please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)
What is the absolute pressure scale?
how much quantity of 1.5" nails and 2.5" nails are required for conventional formwork shuttering?
Which tests are performed on soil to decide the type of foundation to be provided.
Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire
what is the clear cover for shearwall?
What is the procedure and technnology behind jointing of prestessed block in Delhi metro rail project.
If we don't have drawing for Excavation of building,At what rule we will go for excavation and how much depth will go for a villa?
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.
PL.tell me about civil engineering questions with answer
what is meant by sustainable developement as far construction field is considered. Give suitable examples to explain the same