can anyone pls expain me about how can we design a cable
tray??suppose if have to draw a 3 nos of 50 sqmm AYFY and 2
nos of 35 SQmm of AYFY cable through the tray..how can we
design the tray size?? regards...
Answer Posted / 7anoter4
The cable tray is an assemble of tens or hundreds parts.
There are a big number of types and materials involved. You
may get a look in IEC 61537 or NEMA VE-1 or VE-2.
The simple way is to take the construction drawings and to
make a sketch of the cable tray run including the all
derivation on this drawing and then to send this to some
tray manufacturer as B-Line [for instance, you can find
many of them in web or Google].
Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
can we synchronize star system generators with delta system transmission line ? and how ?
How Can You Relate Power Engineering With Electrical Engineering?
how to calculate the change over time for star delta starter for different KW motor?
How can calculate the earthing strip of Copper/GI for rating of 30kV,discharge current 10KA Lightning arrester.
what are the problems that generally occur in power flows??
Minimum IR value of 1.1 kv grade 3.5c (300, 240,185,150,120,95,70,50,35,25) sqmm Aluminium XLPE cable and 4c (16, 10,6 & 4) sqmm cu arm cable between RY,YB,BR,RN,YN,BN,RE,YE,BE & NE.
Dear Brother can u tell the proper size selection of cable & the fault level calculation of braker, busbar etc. pls mail me at azeemk30@gmail.com
What is the effect of positive feedback on stability of the system?
WHAT ARE THE DISADTAGES OF SINGLE-WIRE-EARTH-RETURN SYSTEM USED FOR RURAL ELECTRIFICATION?
what is the interrelation between voltage current torgue speed and magnetic flux in case of different types of electric motors
HOW MUCH CURRENT DOES SYNCHRONOUS MOTOR TAKES AT SYNCHRONOUS SPEED IN NO LOAD CONDITION ?
what is W.T?specify the acceptable range?
what is the difference between gas group b and gas group c electrical equipment construction wise?
what is the most permissible winding temp when we conducting a generator load test?(condition no load)
Why efficiency in thermal power plant is low?