Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answer Posted / abiy
from trapezod forula of area a=h/2*(b1+b2)
a=2/2*(1.7+0.5)=2.2m2
from volume formula v=a*d=2.2*0.15=0.33m3
| Is This Answer Correct ? | 12 Yes | 12 No |
Post New Answer View All Answers
What is meant by autocad?
Which code is used for tor & tmt steel bar?
very simple or less time consuming formula for reinforcement calculation by moment
Hi I had missed my mark list (first year-apr2003)how i search in my old mark details in internet and which web site? pl inform me in full details..
What is the diameter of the 3"inch nails?
Elaborate advantages & disadvantages of using crusher dust instead of sand in rcc work.
what else we can add rather than admixture in concrete to reduce the cement quantity?
how do i remedy a foundatiom that the column bases was cast and aftet 28days crushing the conprehensive strength of the concrete fall below the specification 25N/mm2
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
WHAT IS THE MAIN DIFFERENCE B/W HIGHWAYS AND MOTERWAYS?
what is detail procedure of eccentric footing? plz. give solved exmple?
please, what is the required bar for a column of 6mx6m the dept is 405mmx300mm,its an axially loaded ?
Explain moment of inertia and its importance.
what is pqc
How much for the BRC lapping in full yield and half yield < and which table to get it ?