Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how we can calaculate cutting lengh for stiruups 6mm dia .
column size 20 cm x 30 cm, cover 20mm

Answer Posted / naresh

if columns is 20x30cm
convert 1 cm=10mm
so 20cmx10=200mm
same 30x10=300mm
than
200-40=160 cover block
300-40=260 cover block
=(160+260+10d)*-2d
=(160+260+60)*-60
=900mm
i.e. 90cm (if cover block use in face of stiruups)
or if cover block are using with face of vertical bar of columns stiruups cutting length should be
(160+260+60+10)*2-60=920MM ie 92cm

Is This Answer Correct ?    1 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how to calculate the strength of rebound hammer test reading in building construction ?

3311


how gradation of aggregates effect on slump of fresh concrete?

2292


What is difference between combin footing & rapt footing

1798


cause of cylinder test failure

3246


define the strength

2123


when reinforcement binding completed if there is more cover than the required what is the solution to reduce the cover?

2122


kindly mail me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates plz send my email id- VMANDAL91@gmail.com

1798


IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI

2016


How can we demolish concrete beams?

2255


How to calculate plastering for elevated water storage tank

1230


what is the sequence of the activities in the typical under ground water tank including civil & MEP works.

2374


Labor requirement for each item needed? Lean Concrete 103.550m3 Concrete for Foundation and Structure 1753.000m3 Expansion joint 288.000m Contraction joint 127.000m Dowel bar 450.000m

1695


Material calculation of cm 1:6 for 1sqm

1987


Explain what is Critical Path Method (C.P.M)?

1115


How do You Maintain a structure after getting cube test of low strength.

2276