Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Dear friends, I have a question:
We work on a project which has some boilers to provide steam
for desalination unit.
The boiler area is safe and the only hazard source is the
fuel lines of boilers.
I want to know according to NFPA standard which type of
instrument should be selected on the fuel line: Eex Type or
Non-Eex type?

Thanks in advance

Answer Posted / carl_ellis

I totally disagree. Because NFPA 86 (2007) specifically
states that there is no need to impose requirements for
wiring methods appropriate for a hazardous (classified
area).

------- NFPA 86 (2007) ------------
A.4.1.3.3 Unless otherwise required by the local
environment, ovens and furnaces and the surrounding area
are not classified as a hazardous (classified) location.
The primary source of ignition associated with an oven
installation is the oven heating system or equipment or
materials heated. The presence of these ignition sources
precludes the need for imposing requirements for wiring
methods appropriate for a hazardous (classified) location.
Refer to Section 3.3 of NFPA497, Recommended Practice for
the Classification of Flammable Liquids, Gases, or Vapors
and of Hazardous (Classified) Locations for Electrical
Installations in Chemical Process Areas, and Section 3.3
------------ end ---------------

The 'gas train' or 'fuel train' is a pipe carrying fuel.
It is assumed that the fuel stays in the pipe until it gets
to the burner or is bypassed to an equally secure pilot
fuel line.

Control components in the pipeline typically need agency
approvals for conformance to failsafe conditions, but not
for explosion protection.

Carl Ellis
Measure First

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Q-Explain the different load conditions that will produced different offset which may or may not be acceptable to thhe control function

2229


what is surge and how is it prevented, what is the purpose of bypass valve across AS valve.

2031


Sir , i have completed my M.Sc In Instrumentation and presently working in Maintenance department 3 yrs Exp , is there is any possible for work in offshore ..

1875


what is the responsibility of an instrument commissioning supervisor

3203


NPN transistor, SCR, Zener diode, LED, Varactor diode, Vortex meter, RTD, Resistor, Crystal

2237


In turbine, what does term CDP, NI, NH, HSSOC, means

2852


Q1: Consider part of a control loop, which excludes the transmitter, consisting of a process, a controller and a control valve which may be represented by two dead times of 0.5 min each and three exponential lags of 0.8 min., 1.0 min. and 1.5 min. respectively. We wish to express this system as an overall first order plus dead time (FOPLD) model ie gain, time constant and process dead time. (We will see later that this is often done, to simplify controller tuning). For this exercise, gain is considered to be 1.0. (A) If the transmitter is a flow transmitter whose behaviour can be described by a dead time of 0.2 min. and an exponential lag of 0.5 min. in terms of the overall dead time and overall first order lag how can the system behaviour be approximated ? Overall dead time = Overall time constant = (B) If the transmitter is a temperature transmitter with a temperature sensor in a protecting well whose behaviour can be described by a dead time of 0.7 min. and an exponential lag of 15 min. how can the overall system behaviour be approximated now? Overall dead time = Overall time constant =

1982


how to control pid

1966


What is PDS and PDMS ?

2196


What is critcal speed. what is resonant frequency. why we want to cross crtcal speed on higher RPM (early).

2188


Why is the orifice tab provided?

1293


when the instrument tapping on pipe line is located below and transmitter is located above the tapping point for liquid service transmitter, what should we do, is there any additional drain valve is required??

2226


what is metal of piston ring

1972


what is intrinscily safe system and where we use?

2586


pls suggest suitable MOC of diaphragm for pressure measurement of UREA grade solution service fluid.

3173