what is calculation of cement, snd of 1:4 16mm,12mm plastring
Answer Posted / devineni srinivasa rao
calculation for 100 sq mt
quantity=1oox12=1.2
ratio=1+4=5
dry qty to wet qty=1.5
uneven surface=1.8
cement=1.8/5=0.36x1440=520kgs
sand=o.36x4=1.44 cu mt
| Is This Answer Correct ? | 12 Yes | 1 No |
Post New Answer View All Answers
How can i do RCC rate analysis?
strength of bitumen concrete with 80-100 & 60-70 grade bitumen
How many hours should traffic be not allowed after completing wbm road or bst.and min how many hours should road rollers be used.
Required concret Surface Temperature prior to coating of epoxy pain with references ASTM or ACI whatever
What is meaning of tlc
Caching, Multithreading and RAMBUS are 3 methods for resolving the Bottleneck problem. Please give an explanation for each one (how are they resolve the problem?)
what is your role of in previous company as a construction manager
Define What is made from large rocks, which protects the base of cliffs?
how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.
what will happen if one could not properly follow the spacing of slab reinforcement bar?
List out the types of roofs?
How to get MEP technical,instaaltion & testing data for interview?
What applicable rate of wct in bihar
Special thing in designing a overhead reservoir ? which is different from an ordinary design