how to know 28 day strength of concrete knowing 3 day or 7day strength of concrete???
Answer Posted / ajmal pp
by steam curing we can attain 95% of 28days strength in 3
to 7 days
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
rate analysis for cement pointing 1:4 , for 100 sq m
HOw much % of premium on DSR-2013 currently
At one time what is the height of Lift for concreting for Bridge Piers Class B Loading and refer the code.
what is constat for brickwork
For the calculation of bearing pressure below the footing, to know whether it is below the safe bearing pressure of the soil, the unit of RCC below ground level to be taken is 25 KN/m3 or (25-15)KN/m3, where 25 is the unit weight of RCC and 15 is the unit weight of soil and whether the weight of backfilling to be taken?
please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)
What you understand by richter scale?
how can we calculate steel value, depending on load
How is the leaning tower of pisa supported?
2nd and 4rt angle elevation used in which country ?
give me the rate analysis for Bituminous Macadam and SDBC
What is difference between code and standard and specification?
what is the price of a cubic meter of concrete on international market?
Can inverted beams used in pipes during construction?
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)