Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How Many Brick in One Cubic Meter.

Answer Posted / komalvgarg

its is taken as 500 Nos. in 1 Cum of brickwork.
But when u measure at site it comes from 430-480 Nos/Cum. due to variable sizes of bricks and mortar thickness.

Is This Answer Correct ?    32 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Gidc technical que paper

1771


Dear Sir I Mahesh C. Bhamre have already given a Exam for Superintendent Officer / Public relation Officer Exam Dharmday Aaukta held at Nashik on Date 29/08/2010. My seat no was 5040247. and my cell no is 9822677994. and my mail Id is - mahesh.bhamre@rediffmail.com So can you pl send me details of result of respective exams. Thanking you in Anticipation.

2257


the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm

2351


For making a new road in a village having a school & hospital , tell the steps of construction systemically ?

1649


What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.

2079


In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

2150


Which is the direction of negative angle?

1095


How many feet are in 4 square yards?

1192


Explain the importance of moment of inertia?

1257


RR masonry rate analysis

3345


rate analysis hiring of generator 62.5 KVA

2209


1.Fe500 and Fe550 having more yield strength than Fe415.But why are we prefering Fe415.? 2. d^2/162 formula for knowing the steel wt/m apply all these three? Thanks.

3305


Define What is unit weight of normal concrete?

1289


What is the difference between undo & redo?

1257


Elaborate advantages & disadvantages of using crusher dust instead of sand in rcc work.

1130