what is the ratio of M10,M20,M30,M40,M50,M60 grade concrete
Answer Posted / selvakumar b
M5-1:5:10;
M7.5-1:4:8;
M10-1:3:6;
M15-1:2:4;
M20-1:1.5:3;
M25-1:1:2;
M30-1:1:3;
| Is This Answer Correct ? | 58 Yes | 38 No |
Post New Answer View All Answers
What is proportion of PCC Grade G?
Why should you show Client/Engineer activities clearly on the project plan?
in staad ,why we realease a moment of a member ? what is affect if we realease a moment
How to find out slope footing concrete
what are the ffactors you considered choosing the course?
Slump Values for works?
Currently my house construction is going on but we just realized that the portico earth beam couldn't connect with the original earth because the beam rod not extended so Please advice
HOW MUCH STEEL REQUIRED FOR SLAB OF AREA 23'3"*18.3"? FOR SLAB HOW MUCH DIAMETER BAR WILL USE?
what is the productivity in aluminium shuttering per day
List out some of the software program that can be useful for architect?
how to calculate the material from ratio of work PCC, RRM,POINTING, RCC
Why nautical mile is different from statute mile?
what is right & short method of measurement of slab&beam
how to prepare site mix design
What is componsation