Brick size 230X115X150mm, how many bricks, quantity of sand,
cement required to construct 10 sq mtrs of 115mm thick brick
wall.
Answer Posted / sjtbehera
Brick size- 230 x115x50Consider 10 sqm - 10x.115=1.15cum 115mm th.
Normally mortar joint will be less than 1cm, taking 1cm mortar joint the actual th. Of wall thickness will be-.105mm
So, actual volume- 10x.105=1.05 cum.
No. Of bricks= 1.05/.23*.115*.150=264 nos. Take 5% wastage it comes around 280 nos.
Mortar requirement- total volume of brickwork- 1.05 cum
For fog filling, for use of cut brickwork, uniform joints take 15% extra
So total volume- 1.05+1.05*15%=1.2075
For dry volume, volume increase 1/4 th ofmortar so 1.2075+1.2075/4=1.509 cum
So for 10 sqmt 1.509 cum mortar
If you take 1:6 then you calculated cement and sand
1.509/7=.215 cum
Sand=.215x76= 1.29 cum
Is This Answer Correct ? | 6 Yes | 17 No |
Post New Answer View All Answers
What is the quantity of cement in mix m20 concrete?
How much cement,sand,bricks and water needed for 1square metre brick work?
What is gravity flow?
how to take concrete quantity for precast segment for viaduct project?
silt%= silt volume/ silt+sand volume is this right?
what is the meaning of 40/20 src
How to calculate the area in squarefeets ?How much area of sqft for this measurements?East 53.3ft West 54ft North 47.7ft South 51.1ft ?
Steel requirement in kg of 6" thk slab Total qty 32.64 m3 Beam / column qty 35.39 m3
how can we calculate steel value, depending on load
How to calculate chejja reinforcement
How to calculate concret slab? W l t(4mts*5*2fts) ratio m25 grade pls tell me procedure
cement mortor 1:5 for 30 m2 12 mm tk plastering so how to calcualte its rate
How to calculate the area of a irregular sized land in square feet?and what will be the total area of this land South-51.1ft , North-47.7ft , East-53.3ft , West-54ft ?please explain me how to calculate?
how to calculate labour strength for work for RCC,brickwork,blockwork,in &out plaster,flooring,dado,door frame & shutter,painting etc for constructing highrise building?
How much for the BRC lapping in full yield and half yield < and which table to get it ?