Ok fine let me start with 7 days strength, the provision of 7 Days Strength is now ended over Globally, else in previous version of IS was two third of the characteristics strength and 100% of characteristic strength after 14 days.
There Fore the Deflected Strength for M-25 in:
7 Days 16.67 N/mm2.
14 Days 25.00 N/mm2
28 Days 28.00 N/mm2 (As per Latest Revision of IS 456 Fck + 3)
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
Thumb rule for steel qty for 1m2 in kg/m2 column slab footing beam
Define What is aggregate?
sir please send me campus placement questions in civil engineering
How to calculate steel for beam slab and column
calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick
WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.
how to find the cement bags and sand requirements for the one square meter of internal,external,ceiling plastering by using the various ratios like 1:3,1:4,1:5,1:6
Define the various stages of the project planning process in construction.
What are the important hardware systems used for cad?
Which are the top apps for you civil engineering?
what is directivity effect?
How to improve the strength of fly ash bricks to avoid corner damge? How to get the color lighter similar to normal concrete blocks/
what is the hanekom repairing material after concreting work
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 600 microns?
What is meaning of FREE STANDING STAIRCASE ?