Answer Posted / imran
Ok fine let me start with 7 days strength, the provision of 7 Days Strength is now ended over Globally, else in previous version of IS was two third of the characteristics strength and 100% of characteristic strength after 14 days.
There Fore the Deflected Strength for M-25 in:
7 Days 16.67 N/mm2.
14 Days 25.00 N/mm2
28 Days 28.00 N/mm2 (As per Latest Revision of IS 456 Fck + 3)
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
Explain creep?
What is labor and material payment bond?
What are the applications of cad?
Can we weld hot rolled steel ASTM A615 ? Please Give the detail answer please thanks alot
What is the quantity of cement in mix m20 concrete?
What is the use of offset command?
Calculation of curtain wall of box culvert
How to calculate the quantity of ingredients of M20 grade concrete?
Formula for calculating the volume of bulb in underreamed pile
Does VDF add strength to the flooring apart from preventing water ingress?
how to determine H- zone in a column? where it will occur?
does a b.tech civil engineer fresher supposed to know how to design rcc structure?
How many lbs are there in a yard?
what is cross hair cursor?
How to build the floor to ceiling bookcase?