what is the tool used at construction site for measuring
cement, sand and blue metal in india.

Answer Posted / ratheesh

Measuring box, This size is 1'X 1'X 1'3".
Because one bag cement is 1.25 cft...
also u can measure sand & aggregate.

Is This Answer Correct ?    14 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

can you give me the details of rate analysis of steel and concrete?

2472


What is the Maximum %age of Steel in columns and beams ?

729


what is the Asfalt test?in road constraction..?

1652


How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.

1012


sir when can we expect the AEE results and when will be the interviews sheduled please guide us in this regard thanking you

2010






How to calculate material and labor required for 100 m2 plaster?

1252


TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING

2105


I need old MMUP exam question and answer for Civil engineering

1161


how to identify the failure of building by expansive soils

1234


How many axes do cartesian coordinate system has?

662


what is project?

1927


1. 1. The mass of a chunk of moist soil is 34 Kg and its volume is 0.012 cu. Meter. After drying in an oven, the mass reduces to 14.25 Kg. Determine the water content, the density of moist soil, the dry density, void ratio, porosity and degree of saturation. Take G = 3.25

2147


it is possiblee to produce concrete with out cracks...

1486


Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required

1549


whats is difference between anchorage length and development length

1379