Why start up vent is
fully kept open when
boiler is lighted up?

Answer Posted / a.h.z

in the start up the main steam valve closed so there is no
way for wet steam or hot water to discharge except start up
vent to protect the boiler pipes till the superheat steam
consist and pressure raise to turbine the start up vent
closed and main steam valve open to turbine.

Is This Answer Correct ?    2 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

can any body sand me previous exampapers of jr. engineer (mechanical)

1982


PLEASE PROVIDE ME PAPER ALONG WITH QUESTION THAT ARE ASKED IN ENTRANCE EXAM EVERY YEAR/

1789


hi friends kumar here if anybody of u have essar placement papers than plz send it to me i need it urgently..ok mail id is kskalyani@gmail.com

2029


SOMEONE POST THE MODEL APTITUDE QUESTIONS FOR MRF TYRES PLz pLZ pLZ ..Very urgent

5924


asked about the power transimmisions and types of power drives and about milling different process types and differnce between straddle milling and gang milling

2091


• How can you justify it?

2157


hi friends pls send the bhel question papers is very urgent...

2365


Please mail me the Satyam Computers (Mechanical Division, Satyam Technologies, Hyderabad & Bangalore) question papers on Design & strength of materials. Will be very thanksful.....srinivas_1704@yahoo.co.in

2100


sir can u plz send me Jindal Steel's mechanical engg. paper and the aptitude paper of previous year....i wud be very thankful to u.... my email id..- suraj.candid@gmail.com

2171


RRB exam model questions pls forward.

2032


CAN ANY ONE SEND ME THE RRB SECTION ENG. Q-PAPER .. MY MAIL ID :suresh25siva@yahoo.com, suresh.sivakumar@tcs.com

2154


How to convert GSS duct volume in KG for all guages

3284


Study the attached ACS 790 AHU and boiler GUI and refer to the video on the software usage, catalog and the step by step document (page 9) to perform the following task: List in a table form the controllers and all their connected I/O for the boiler and the AHU.

1517


sir please send previous question papers of technician grade III of all rrb's. thank you

2144


junior engineeer (railway previous questions)

1993