how to calculate the quantity of plaster.
Answer Posted / manoj kumar bhola
Quantity of plaser for 12 mm thickness of ratio 1:6 say for 100 sqmt then ,the value 2 takes for total dry volume(cum)
2/1+6 =0.29 cum(8.28 bags)cement=4.14 kg/sqm
=0.29 * 6 =(1.74 cum)sand
similarly for Quantity of plaser for 20 mm thickness of ratio 1:6 say for 100 sqmt then ,the value 3 takes for total dry volume(cum)
3/1+6 =0.43 cum(12.29 bags)cement=6.15 kg/sqm
=0.43 * 6 =(2.58 cum)sand
| Is This Answer Correct ? | 4 Yes | 1 No |
Post New Answer View All Answers
material used for mendrel use to bend epoxy coated rebar
types of laps in column
sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience
how is the reinforcement is distributed in triangular slab
How do you calculate the power of a centrifugal pump?
how the calculation occurs if i want to mix 1cum of M50 concrete. please calculate every ingredients with detail calculation.
a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.
What does civil engineering mean?
what is the 0 value in quantity surveying
If density of cement is 1500 Kg/m3, the how is specific gravity 3.15 ? (Density of water is 1000 Kg/m3)
what is the cost difference of a same structure when it is constructed with brick masonary and when it is constructed with block masonary and concrete as a frame structure????????????????????????
. Write a C program to perform following functions:- a. Declare one integer variable of all the storage classes. b. Print all the variables without assigning any values in tabular format. a. The tabular format must contain the variable name, type, storage class and printed value on the screen in RED color.
What is the cost difference between site mix and ready mix concrete per cubic meter
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum
what is tension column?