what is the actual productivity of carpentor,fitter,masson
for brickwork and masson for plaster etc
Answer Posted / pradeep muley
1 fitter with 1 helper - 100 kg per day cutting, bending & placing,
Mason - 100 to 150 Sqft per day
Is This Answer Correct ? | 91 Yes | 23 No |
Post New Answer View All Answers
how much need sand and cement for 1 cft roof construction?
explain fie benefits of using standard terminology in the measurement process
How do you calculate reinforcement weight of steel?
brickwork labour rate per cum ?
what is the types of door's wood?
do we decide reinforcement steel , based on bending moment ? give example with continous slab?
how to compute slab reinforcements on step by step procedures??
Define What is the difference between routing maintenance and major maintenance in school facilities?
find the discharge of water through a horizental venturimeter having 400mm dia at the inlet main and 150mm dia at thorat.if the diffrential gauge between inlet and thorat shows a pressure head of 25cm mercury. assume coefficient discharge 0.98 and specfic gravity of mercury as 13.6.
The properties of concrete HA-30 and how does it differ with M 30 (specify the important characteristics like workability,strength,mix design,slump test value)and what is the standard relating to it
How to make tiles floor step by step procedure?
Explain soil analysis?
Please let me know what is the simplest way of Calculating Mix Designs
Is it worthwhile to carry out tests on particle density of soil particles for geotechnical design?
Why you are leaving present job?