what is the actual productivity of carpentor,fitter,masson
for brickwork and masson for plaster etc
Answer Posted / n.v.ramana
1)CARPENTER=150SQFT.
2)FITTER=250KG/DAY
3)MASON=300BRICKS OR 1CUM
4)MASON-PLASTER=200SQ.FT/DAY.
| Is This Answer Correct ? | 33 Yes | 55 No |
Post New Answer View All Answers
How you read 5x3x1 #4 @ 20" 0/C in steel structure?
Where is the worlds longest elevator and how long is it?
which red: used in roof teping, then use only cement
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
What is type failure of road surface? how to repair the failure of road surface?
What is unit weight of normal concrete?
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 600 microns?
how to calculate the strength of rebound hammer test reading in building construction ?
how to calculate MR 9(derivation)
how many mason and labaur work for a 1 brass bricks plz let me know the calculate & how to made calculation for this and whats the formulas for this?
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)
How to calculate chejja reinforcement
I need to constructive work in amaraj batteries
Critical Path Method is...
What is the strongest bridge for a school contest?