Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.

Answer Posted / r. dilli babu

Input is insufficient.size of the column is missing.
If size of the column is 300 x 300 mm, then the volume will be
=h/3(A1+A2+Sq root of A1square+A2square)
=((.5-.15)/3)(.09+3.4+(sq root of(.09 square + 3.4 square)))
=.116(3.49+(sq root of (11.5681))
=.116(3.49+3.401)
=.116*6.891
=.799 cum

Is This Answer Correct ?    8 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the difference between chamfer and fillet?

1379


If density of cement is 1500 Kg/m3, the how is specific gravity 3.15 ? (Density of water is 1000 Kg/m3)

2282


Explain what is change order request?

1080


why do we provide haunches in rcc box or underpasses?

2932


WHAT R THE GENERAL TECH QUESTIONS ASKED FOR THE INTERVIEW FOR AN AUTOMOBILE INDUSTRY,SPECIALLY DESIGN DEPT

2557


What is the ideal size of the living room ranges from small to large size?

1069


How can we demolish concrete beams?

2251


how calucate cement sand ratio for plstering

1912


how many type of admixtures for water stored structure?

2066


What is absolute pressure? How absolute pressure is calculated?

1071


what is tension footing?

1924


what is the difference between prime coat and tack coat in road construction

4989


For 1 bag cement how i will calculate sand and metal aggregate;Here the mix proportion is 1:2.49:2.38

1831


Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––

2344


 Which Types Of Bricks ? 

2952