How to Concrete cube test method and required result in
3days & 7days & 28 days, for all grade of concrete which
refer the is code no.
Answer Posted / a.k.pathania
Concrete cube testing is done using compression testing
machine. Cubes of dimensions 150x150x150mm are casted and
cured properly and tested for 3,7 & 28 days strength. You
can refere codes- IS 516 for cube testing and IS 456 for
concrete-general. Also refer SP-23/24. Concrete mix design
can be done with IS10262.
| Is This Answer Correct ? | 13 Yes | 3 No |
Post New Answer View All Answers
i have a interlock pavement work.i need to compact about 2000 sq metres of sub base grade c of thickness 15 cm.what is the amount of water required for compaction ??
What is Architect-Prepared Contract?
How to calculate Acctually Brickwork Quantity in Honey Comb Brick in circular Soak Pit
Which stone is best for wall construction Laterite Stone or Cement Blocks
What is the usage of zoom command?
Why nautical mile is different from statute mile?
contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?
types of laps in column
Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....
Questions related to civil.engg in company
Describe the sections included in a typical bill of quantities
What is the difference between 53 grade and 43 grade cement
how much repeitation for conventional and maivan formwork?
What is type failure of road surface? how to repair the failure of road surface?
Is it possible to make a feature using an overdefined sketch?