How to Concrete cube test method and required result in
3days & 7days & 28 days, for all grade of concrete which
refer the is code no.
Answer Posted / a.k.pathania
Concrete cube testing is done using compression testing
machine. Cubes of dimensions 150x150x150mm are casted and
cured properly and tested for 3,7 & 28 days strength. You
can refere codes- IS 516 for cube testing and IS 456 for
concrete-general. Also refer SP-23/24. Concrete mix design
can be done with IS10262.
| Is This Answer Correct ? | 13 Yes | 3 No |
Post New Answer View All Answers
What are the benefits of rcc pipes over steel designed pipes?
What is the meaning of soil reinforcement?
satart to end steps by step process of building construction...? i want to planning theme accuretly
in the earthquqke the profile of water on dam is parabolic or not
what will be the cost of thickness of 125mmor rcc measurement of 52x33.75 feet
pls mail some more tecnical qustions at msaranya2610@gmail.com
What is quantity of cement and sand required for 2000sqft of tiling?
Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire
Which ratio use for cement selery???
How many mortar required for Brickwork of 1 Cu.m works??
Formula of mid span bar
How is the strength of cement measured?
Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)
My daily concrete volume of M25 concrete is 1st day= 25 Cum 2nd Day = 45 Cum 3rd Day = 55 Cum 4th Day = 22 Cum 5th Day =72 Cum 7th Day = 49 Cum. What will be acceptance criteria of concrete considering as per is 456 cl.15 and table 11 (cl 16.1 and 16.3).