In control valve , Failure position : Close
If it is Fail close(FC) during failure of AIR.. what will be the initial/ normal position of control valve is it normally open or close? please some one explain soon..
Answer Posted / bhargav purohit
Hi,
I think your question has it self an answer. Your valve is Air fail to close. Means if there is no Control Air/signal, your valve will be closed .
In running plant condition, Position of valve could be anything according to process.( Fail to open or close depends on process requirement)
Suppose you want maintain a Tank level and safe condition is full tank, then..
1> if you are maintaining level by inlet water flow to tank, your valve should be Fail to open. Means in case of signal failure your valve will open and fill the tank (Safe condition)
2>If you are maintaining level by output flow, then you should select fail to close vale. So in case of failure of control signal, output flow will be closed and tank will be full.
Regards,
Bhargav Purohit
| Is This Answer Correct ? | 12 Yes | 0 No |
Post New Answer View All Answers
What is mean by analytical instrumentation?
Identification of ss fittings, pilot valves, relief valve.
Emergency Shutdown Systems/ Plant Shutdown System.
need to calculate flow rate with the help of dp range and orifice bore dia and size. range is 0 to 400 inwc and orifice size is 12 inch 150 # rf and bore dia is 7.180 inch. need to calculation for flow rate
Explain the burnout feature.
Punj lloyd is coming in our Jadavpur Universtiy campus for campus placement. Please send me some hints about the writtend exam. My email id is subratafriends@gmail.com
How we connect a instrument with ground, Give brief explanation with help of diagram?
what is the reset offset and control system in instrumentation
WHY THE DEGREE OF VALVE PLUG AND VALVE SEAT IS SLIGTLY DIFFERENT I CONTROL VALVE TRIM DESIGN
what is a half wave, full wave, and bridge rectifer.
what is moisture probe? What are there types? What is there working principle and how they works? guys this is one of technical question I had ask in interview. If you know its answer please let me know. The interviewers were more interested in microwave moisture probe, so if you find its any link please just forward me on my mail id.avinash1200@gmail.com Thanks in advance.
sir,would you please send me the Hindustan petroleum corporation limited papers(HPCL).my e-mail ID is ujjwal_sharma1983@yahoo.com
Why MUX JB's are using only Temperature Element in Fundation field bus?
Describe how to use megger to measure the earth resistance and insulation resistance
installation process of orifice,a question asked for confusion creation in interview by BARC 1.if orifice is tightly fitted with pipe ,it will act like venturi 2.if orifice is left hanging in between liquid it will not create the pressure difference exactly,