how much brick,cement,and sand required in 1cum
brickwork(1:4)
Answer Posted / suneel.p
brick size 0.23*0.1*0.1(1:4)
valum of brisk : 0.0023cum
say 12mm thick mortar or brick layar((0.23+.0006)*(0.1+.0006)*(0.1+.0006)
so volume of brick: 0.00265
no.of bricks in 1cum=1/0.00265=378 no.s
volum of brik for 1cum=378*0.0023=0.869cum
volum of mortar 1-0.869=0.131
add30% for dry mortar of =0.30cum
add 10% for wastages =0.10cum
total volum of mortar =0.40 cum
for c:m =1+4=5
qantay of cemant 1/5*0.4=0.08 cum
1cum of cemant =(1440/50)=28.8bags
=.08*28.8=2.304bags
sand =4/5=0.8*0.4=0.32cum
| Is This Answer Correct ? | 16 Yes | 19 No |
Post New Answer View All Answers
how many spacers we need for 1 ton reinforcement? aprox.
what is concrete canvas?
What is the zero value in quantity surveying
When column of building is abutting the boundary line,then suitable footing advised is
Howmuch bend to be provide for 200/600 BEEM
.5Ast
is it fair to recruit another prestressing agency once earlier agency has provided guide cone for post stressing the Concrete -I girders? It is observed that the bearing plate of another agency is not matching with the earlier one resulting in protruded strands after stressing from the face of girder. Kindly advice.
Trapezoidal section footing calculation of Volume & its Area
The properties of concrete HA-30 and how does it differ with M 30 (specify the important characteristics like workability,strength,mix design,slump test value)and what is the standard relating to it
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
"Gates of the dams are generally designed of curved shape". Why?
why we use aggregate,sand with cement in concrete?
how to check and keep control on the wastage of material at site
What are the Types Of DPC and its Thickness used?
Form where IS456 is adopted in 1978?