how to calculate concrete qty for footing using M25 grade
1:1:2 for 731 cft.
Answer Posted / s jaikumar
For 1m3 of 1:1:2
Cement 1.5/4=0.375/0.036=10.41
Sand 0.37
Agg 2 *0.37 =0.74
So for 731cft /35.28=20.71
Cement is used 10.41*20.71=215.59 bags
Sand is used 0.37*20.71=7.66m3
Aggregates is used 0.74*20.71=15.32m3
| Is This Answer Correct ? | 1 Yes | 4 No |
Post New Answer View All Answers
what do you mean by yeild stress of a material? What will happen when hit is given to cement?
what is the metal ratio in granular subbase coarse for one cum ? And please explain the morth table ...what is the difference between grading 1 , 2, 3 what it means..plz explain
How to determine thee cut length for steel reinforcement bars in R.C.C design
what is differences between ferrock and concrete ?
What are some facts about concrete?
can i make bricks using M10 grade concrete ? and what would be the cost of a brick if we use m10 grade concrete sand and aggregates ??
what else we can add rather than admixture in concrete to reduce the cement quantity?
mix design procedure for 1:6 cement mortar
What are the advantages of cad?
1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.
What is the use of water table & Kreb stone for drain
Explain what is Hybrid Foundation?
Explain the Strength of brick?
what are the Task work of different labour.?
how to calculate total cost for slab 35'×8'