how to calculate the number of cement bags required for 1m3
of work
Answer Posted / pradosh pradhan
FOR M20 = 1:1.5:3
CEMENT = 1/5.5*1.57=.285 CUM.
AS PER CIVIL ENGG 1 CUM CONSUME 1440KG=28.8 BAGS
SO 0.285 CUM = .285*28.8= 8.2 BAGS
Is This Answer Correct ? | 3 Yes | 6 No |
Post New Answer View All Answers
five benefits of using standard terminology in the measurement process
Material calculation of cm 1:6 for 1sqm
How high should the water tank be to provide a 60 psi at base of this water tower?
What is the procedure of concealed plumbing in toilets?
How and where are aqueducts built?
What is labor and material payment bond?
What is thumb rule for deep trench excavation
How should we design a brick column and footing?(note: no reiforcement to be provided) Can you tell me any reference book where i could possibly find this design? Plz help urgently
What the advantages and disadvantage of using 90mm and 100mm bricks for a wall of a house? Thanks for any input.
what is detail procedure of eccentric footing? plz. give solved exmple?
pls tell me , what is the water content
What are the uses of alloys in daily life and how are alloys made?
Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
Define different types of roof systems?