how to calculate the number of cement bags required for 1m3
of work
Answer Posted / pradosh pradhan
FOR M20 = 1:1.5:3
CEMENT = 1/5.5*1.57=.285 CUM.
AS PER CIVIL ENGG 1 CUM CONSUME 1440KG=28.8 BAGS
SO 0.285 CUM = .285*28.8= 8.2 BAGS
| Is This Answer Correct ? | 3 Yes | 6 No |
Post New Answer View All Answers
what is the breaking strength of wall tiles
What do you mean by tolerance factor of concrete ?
How much cement and sand are required for 1 square feet of plaster at a thickness of 15 mm at a ratio of 1:4?
What is the standard volume of pharma in cub ft
explain fie benefits of using standard terminology in the measurement process
what is civil engineer greatest strength and weakness?
how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
why development length = 50D . why not 100D
why we use for testing of compression strength concrete the size of specimen 150x150x150. why we are not using another dimension like 100x150x100 uneven dimension.
What is a projection line?
What is Heavy Concrete & Normal Concrete
Who built the sears tower?
What is the coeffiencent Friction Angle between Steel and Ashphalt?
when reinforcement binding completed if there is more cover than the required what is the solution to reduce the cover?