How we calculate the cement for the M 15 normal concrete with
aggregate size is 40 mm ?
Answer Posted / mangesh
for M15 proportion is 1:2:4
assume wet volume 1 m3 of work
to produce 1 m3 of wet volume we need 1.54 dry volume
cement qty=1.54/1+2+4=0.22 m3
hence no of bag=0.22*1440/50=6.33 nos
sand qty=0.154*2=0.308 m3
agg qty=0.154*4= 0.616 m3
40 mm is max size of agg & it is the std value
Is This Answer Correct ? | 5 Yes | 6 No |
Post New Answer View All Answers
Howmuch bend to be provide for 200/600 BEEM
Define What is an ice dam sock?
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?
Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.
within an emergency scenario what are the safe systems of work a coss can setup as part of is duties
Why the finite element method is lower bound solution?
What is meant by solid geometry?
How to calculate sand , cement quantity for 23mm thk brick work(10x10)
In which code the the maximum height of concrete casting has been explained
what is education Cess.
5. Do you feel that your present employer estimates your full work potential? Are they pleased with your work performance?
What is chemical composion test
what is that one cub metre plaster in cemant and fine sand
Will water damage concrete?
what is meant by residual strain?