How we calculate the cement for the M 15 normal concrete with
aggregate size is 40 mm ?
Answer Posted / n3
for M15 proportion is 1:3:6
assume wet volume 1 m3 of work
to produce 1 m3 of wet volume we need 1.54 dry volume
cement qty=1.54/1+3+6=0.154 m3
hence no of bag=0.154*1440/50=4.44 nos
sand qty=0.154*3=0.462 m3
agg qty=0.154*6=0.924 m3
40 mm is max size of agg & it is the std value
Is This Answer Correct ? | 4 Yes | 10 No |
Post New Answer View All Answers
Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....
what is the difference between tsp & tower
Please tell me the quantity of cement, sand, flyash, foaming agent required for 1 cubic meter of cellular lightweight concrete blocks. also , is there any admixtures required for the CLC blocks production.
Elaborate advantages & disadvantages of using crusher dust instead of sand in rcc work.
can i make bricks using M10 grade concrete ? and what would be the cost of a brick if we use m10 grade concrete sand and aggregates ??
How many square meter can mason layout chb per hour
My daily concrete volume of M25 concrete is 1st day= 25 Cum 2nd Day = 45 Cum 3rd Day = 55 Cum 4th Day = 22 Cum 5th Day =72 Cum 7th Day = 49 Cum. What will be acceptance criteria of concrete considering as per is 456 cl.15 and table 11 (cl 16.1 and 16.3).
how do you calculate the length of "L" of main & distribution bar for reinforcing of raft footing
How do you determine specific gravity of cement?
The properties of concrete HA-30 and how does it differ with M 30 (specify the important characteristics like workability,strength,mix design,slump test value)and what is the standard relating to it
What is specific gravity???
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
How can you distinguish between sorption, absorption and adsorption?
57. Calculate the volume of a truck loaded with stone chips whose data are as follows– 5 Top Length - 13-9, 13-10, 13-09 Bottom Length - 13-11, 13-10.5, 13-10 Top width - 8-7.5, 8-8, 8-7 Bottom width - 8-7, 8-8, 8-7.5 Depth - 2-0, 1-11.5, 1-10, 1-11, 1 -10.5, 1-11.75, 1-11
Prepare a Schedule for a Highrised building from starting stage to Handover?