How we calculate the cement for the M 15 normal concrete with
aggregate size is 40 mm ?
Answer Posted / n3
for M15 proportion is 1:3:6
assume wet volume 1 m3 of work
to produce 1 m3 of wet volume we need 1.54 dry volume
cement qty=1.54/1+3+6=0.154 m3
hence no of bag=0.154*1440/50=4.44 nos
sand qty=0.154*3=0.462 m3
agg qty=0.154*6=0.924 m3
40 mm is max size of agg & it is the std value
| Is This Answer Correct ? | 4 Yes | 10 No |
Post New Answer View All Answers
what is tension column?
When column of building is abutting the boundary line,then suitable footing advised is
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..
please give me the rates of RCC(CUM), PCC(CUM), Brick Work(CUM), Tile Flooring, Saria Shuttering
If density of cement is 1500 Kg/m3, the how is specific gravity 3.15 ? (Density of water is 1000 Kg/m3)
Define What is unit weight of normal concrete?
What do you mean by tolerance factor of concrete ?
Spider cracks occur in beam bottom due to––
How do you convert wind speed into force?
what is the type of earthing
How many times we can use Fresh bentonite ford wall execution? Would like to know the clear concept of recycling. After flushing can we use it for another time time for flushing? Or we have to use it for for excavation only?
What is the quantity of cement used for stone pitching work of 100sqm 225mm thick and cement mortar of 1:6? And how?
3. What are the disadvantages of your present job, things you do not like about it?
How to produce the Concrete Grade 30mpa at 12hour? How to prevent for plastic shrinkage crack? How can we produce fire resistant concrete?
Define What is the tensile strength of wood?