how you calculate the qty. of cement ,sand,aggregate from
proportion 1:2:4 M15

Answer Posted / vinod kumar,sriharikota

quantity of cement = 1/7=0.1428 cu.m

quantity of fine aggregate = 2/7 =0.2857 cu.m

quantity of coarse aggregate = 4/7 =0.5714 cu.m

total = 0.1428+0.2857+0.5714 = 1.000 cu.m

Is This Answer Correct ?    3 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Curvature ki quantity kaise nikalte hai pls give me ans... curvature canal ka hai

2564


how much of the strength comes from post-production curing

1856


Exterior Joints,define

1516


Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day

1576


how many material required for brickbat water proofing of toilets.

1579






How do you calculate reinforcement weight of steel?

657


What is bylayer?

672


Detection of a beam & a girder are––––

1769


For 1 bag cement how i will calculate sand and metal aggregate;Here the mix proportion is 1:2.49:2.38

1398


what is the productivity in aluminium shuttering per day

1561


what is raft foundation

1123


What is the use of mirror command?

738


Why was the empire state building made of steel?

673


brickwork labour rate per cum ?

1093


How can i display 5 asterisk and another 5 asterisk )?

2065