how you calculate the qty. of cement ,sand,aggregate from
proportion 1:2:4 M15
Answer Posted / vinod kumar,sriharikota
quantity of cement = 1/7=0.1428 cu.m
quantity of fine aggregate = 2/7 =0.2857 cu.m
quantity of coarse aggregate = 4/7 =0.5714 cu.m
total = 0.1428+0.2857+0.5714 = 1.000 cu.m
Is This Answer Correct ? | 3 Yes | 3 No |
Post New Answer View All Answers
Curvature ki quantity kaise nikalte hai pls give me ans... curvature canal ka hai
how much of the strength comes from post-production curing
Exterior Joints,define
Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day
how many material required for brickbat water proofing of toilets.
How do you calculate reinforcement weight of steel?
What is bylayer?
Detection of a beam & a girder areββββ
For 1 bag cement how i will calculate sand and metal aggregate;Here the mix proportion is 1:2.49:2.38
what is the productivity in aluminium shuttering per day
what is raft foundation
What is the use of mirror command?
Why was the empire state building made of steel?
brickwork labour rate per cum ?
How can i display 5 asterisk and another 5 asterisk )?