how you calculate the qty. of cement ,sand,aggregate from
proportion 1:2:4 M15
Answer Posted / vinod kumar,sriharikota
quantity of cement = 1/7=0.1428 cu.m
quantity of fine aggregate = 2/7 =0.2857 cu.m
quantity of coarse aggregate = 4/7 =0.5714 cu.m
total = 0.1428+0.2857+0.5714 = 1.000 cu.m
| Is This Answer Correct ? | 3 Yes | 3 No |
Post New Answer View All Answers
In the roof of a pumping station explain briefly the components of a waterproofing system?
what is the painting co efficient of slope roof tiles?
5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)
Define What is the best type of wood glue?
if dia of slab beam bar is38mm what its clear cover any method of provide clear cover
Suppose you planning to paint newly fabricated workshop building made of structural steel of 10 tons total mass. How many litters paint primer for 1 coat and 2 coat of top coat?
what is the breaking strength of wall tiles
What is the amount of work done by a carpenter, bar Bender and plaster Mason in interior and exterior plaster
What is the different type of slump test indications?
What is the ideal size of the living room ranges from small to large size?
calculate the quantity of water for 1:6 cement mortar
What is the nature of duties & responsibilites senior civil engineer ?what is self confident & satisfaction should be a senior civil engineer?
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
what is BPM in concrete demolition hammers. what is better a higher value or lower
how much to get of BRC lapping in full yield and half yield ?