i have a dp tx range is 5000mmwc. in which calibration i use in a open tank.1.5*3.5*2.5 mtr.for level msmnt. what is the calculation.
Answer Posted / raj
Open tank level calculation = tank hight * density
Example for
3 meter tank hight
Process liquid for disel density 0.7
So calculation
3 * 0.7
2.1 meter
LRV. O
URU 2.1 meter if you wand change to mmh2o the unite
| Is This Answer Correct ? | 11 Yes | 1 No |
Post New Answer View All Answers
What is the GK Value in Flowmeter?
Can anybody tell me which type of question are asked in the interview for the FORMULATION(Pharma) as a instrumentation engineer, & question in building managment system.
hiii.... can any one provide me previous years question paper of hindustan petroleum for instrumentation engineering???
what is diffrance between FF & SMART, explain with difination
How to erection of DCS Panel at site step by step
I have 0.75mm sq multicore cable (IS type) , can use instead of same type but 1.5 sq mm cable ? Note : The distance is around about 150 meter.
What happen if I install my pressure transmitter below the elevation of pipe in natural gas service?
I am having a Phoenix digital to modbus converter. The o/p of the same is connected to flow computer FB407. But the digital signals are updated only after one minute in the flow computer. what may be the cause of delay in communication? Flow computer is having a scanning period of less than 1 sec.
A PLC is programmed to drive three motors A, B and C as follows : After running motor A for an hour, motor B should get ON and motor A should get OFF. And after running motor B for an hour, motor C should get ON and motor B should get OFF. And after running motor C for an hour, motor A should get ON and motor C should get OFF. (That is, a cyclic repetition with time period one hour) Now, the second condition is: If any motor gone faulty and is tripped, the consecutive motor should get ON and the faulty (tripped) motor should be eliminated from cyclic repetition. The remaining two motors should bear the cyclic repetition of one hour each. (For healthy motor take logic as high and for tripped motor take logic as low) Now, the third condition is: When motor A load(Amps) exceeds 60% of its rated load, motor B should get ON in parallel to motor A. And when both motors A & B are running in parallel, and if their load exceeds 60% of their rated load, motor C should also start in parallel to A & B. [Here the cyclic repetition is eliminated, until their loads become normal(40%)] [Take logic high(1) for load at 60% and logic low(0) for load at 40%] Now draw a flow chart or a ladder diagram to fulfill the above condition.
What is the right procedure for adjusting the gap voltage of bently nevada vibration sensor?
How to calibrate smoke Dectector
we are using centum vp as monitoring with Dell precision work station T3600 but some times PC(s) are restarted automatically . how we can solve this problem? thanks
send me model hpcl questions pleas..........my mail id mohideen.dharvesh@gmail.com
I want to know about DDCMIS in detail ? please explain it. Also give name of reference books in which it is explained in detail in very simple manner.
why I need valve guard and whats different between guard and positioner ??