actually dia of the bar reduce asper drawing spacing also
decrease that time so how to calculate the spacing of with
respect to changed bar dia?
Answer Posted / s.abdul ajees,v.srinivasan
ACTUAL DIA OF BAR AREA/CHANGE DIA OF BAR AREA x ACTUAL SPACING
EX:
AS PER DRAWING 20MM DIA (AREA=3.14X(20^2)/4 =314.16MM^2
CHANG OF RAD 16MM DIA (AREA=3.14X(16^2)/4 =201.06MM^2
ACTUAL SPACING 200MM
=201.06/314.16X200
=127.99MM SAY 120MM C/C
SPACING OF BAR = 120MM C/C
Is This Answer Correct ? | 7 Yes | 1 No |
Post New Answer View All Answers
what might be the problem faced in the near future if the M-sand is used in the place of river sand during wall plastering? (As per IS)
the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm
What is M40 _ TOR - EQ and B.F.S
What do you meant by gui?
What is the use of water table & Kreb stone for drain
sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience
What is difference between engineering stress and true stress?
Please design 12.5m long dubbly beam
115mm thickness brick work how to required mortar
Design a shear wall of length 4.20 m and thickness of 250mm subjected to the following forces.Assume Fck = 25Mpa and Fy = 415Mpa and the wall is a high wall with central part 3440mm x 250mm and two 380mm x 760mm strong bands at each end with following loading. S.No. Loading Axial force Moment Shear 1 DL+LL 1950 600 20 2 Seismic load 250 4800 700
what motivates you to do a good job
important question on stones
IS STEEL BARS IS AS PER ISI TRANSVERSE RIBS SHOULD BE UNIFORM IN DISTANCE, PLEASE EXPLAIN WHY,
What is the use of array command?
What is the exception critarea of cube?